Name : Railadevi Lake.
Avg. Lake Size : 8 Hectares, 5 meters deep.
Location : Maharastra, India.
Bioclean PC 101 used : 2200 kg.
Remarks :

The Top layer and the Bottom layer of the water column in the lake was monitored along with the sludge analysis for a period of 24 months. The results are shown in the form of graphical representation.

Before Bioclean Pond Clarifier Treatment
6 months after Bioclean Pond Clarifier Treatment
Graphical Representation